SOLVED

Recurring Tasks in MSP

New Contributor

How to set a recurring tasks of frequency more than 1 year? Let us say 18 months frequency of aero engines maintenance

Thank you

1 Reply
best response confirmed by Dale Howard (MVP)
Solution
Ulhas_pmskills,
For something like that your best option is to do it manually, there is no automated functionality to do anything greater than yearly.
John