Recurring Tasks in MSP

%3CLINGO-SUB%20id%3D%22lingo-sub-3009337%22%20slang%3D%22en-US%22%3ERecurring%20Tasks%20in%20MSP%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-3009337%22%20slang%3D%22en-US%22%3E%3CP%3EHow%20to%20set%20a%20recurring%20tasks%20of%20frequency%20more%20than%201%20year%3F%20Let%20us%20say%2018%20months%20frequency%20of%20aero%20engines%20maintenance%3C%2FP%3E%3CP%3EThank%20you%3C%2FP%3E%3C%2FLINGO-BODY%3E%3CLINGO-SUB%20id%3D%22lingo-sub-3009532%22%20slang%3D%22en-US%22%3ERe%3A%20Recurring%20Tasks%20in%20MSP%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-3009532%22%20slang%3D%22en-US%22%3EUlhas_pmskills%2C%3CBR%20%2F%3EFor%20something%20like%20that%20your%20best%20option%20is%20to%20do%20it%20manually%2C%20there%20is%20no%20automated%20functionality%20to%20do%20anything%20greater%20than%20yearly.%3CBR%20%2F%3EJohn%3C%2FLINGO-BODY%3E
New Contributor

How to set a recurring tasks of frequency more than 1 year? Let us say 18 months frequency of aero engines maintenance

Thank you

1 Reply
best response confirmed by Dale Howard (MVP)
Solution
Ulhas_pmskills,
For something like that your best option is to do it manually, there is no automated functionality to do anything greater than yearly.
John