Forum Discussion

APS1979's avatar
APS1979
Copper Contributor
Jan 11, 2022

Project Server Licenses

Hi, hoping someone can clarify a licensing question ASAP. We need to know is a Client Application License (CAL) applied to/needed for every named Enterprise Resource created.   Are license costs d...
  • Paul_Mather's avatar
    Paul_Mather
    Jan 12, 2022

    Hello APS1979 ,

    Login is defined as any user who accesses the PWA web interface - PWA homepage, timesheets, project center, Project sites, Issues lists, Risks lists etc. A resource that is just named on a task and is not a user who logs in to PWA, won't need a CAL.

    Paul