Aug 24 2022 07:29 AM
Hi
I am currently using the desktop client version to prepare and update the project plan. Once i have completed the updates, i would like to save the updated plan in Project Online. I am not sure how to go about doing it.
I tried the following steps, but the plan is not getting updated in Sharepoint.
1. Click on "Save As"
2. Select "Sync with Sharepoint"
3. Select "Existing Sharepoint Site" in the "Sync with" option
4. No changes to the "Site Address".
5. No changes to the name of the project plan file.
6. Click on "Save"
I see a progress window that mentions "Updating Sharepoint and project".. once it completes, I go to Sharepoint to check if the project plan is updated, but don't see any changes to the existing plan in Sharepoint.
I am new to project online tool as well as Sharepoint; so I am definitely doing something wrong or missing a step.
Aug 24 2022 07:57 AM
Aug 24 2022 08:00 AM
Aug 24 2022 08:33 AM
Aug 24 2022 08:34 AM
Aug 24 2022 08:37 AM
Aug 24 2022 08:42 AM
Aug 25 2022 08:52 AM
Aug 25 2022 09:12 AM
Aug 25 2022 09:28 PM
Sep 06 2022 04:36 AM
Hi @Dale Howard
Been trying to figure out the best option to have the Project Desktop features to do the planning and tracking of the project, but instead of having it in the desktop, would like to have the plan in Project Online.
Frankly, I am just confused as I have been scrounging around to find some article/video to get to my goal.
One option, that I thought of but I am not sure if this is the right way:
1. Click on the "Save As" option in Project Professional (Desktop client) and select "Sync with Sharepoint".
2. Go to Project Center (where I hope the project would have got saved)
3. Check out the project and update the project plan with the Project Professional Client.
4. Check in the project, once changes are done.
The issue being is that when i click on "Save As" to "Sync with Sharepoint", i get the following error message.
Sep 06 2022 05:48 AM
Sep 06 2022 06:37 AM
Thanks @Dale Howard. I will reach out to my IT administrator, who is also the admin for Project Online. Will come back to you, once we have the setup done properly.
thank you so much for the guidance and the help..
Sep 06 2022 09:07 AM
SolutionSep 14 2022 08:22 AM
Hi @Dale Howard
Wanted to circle back to you and keep you informed that we have been successful in getting Project Online up and running. We got the help of the MS Tech support executive.
Thanks a lot for all the guidance in helping me out with this issue..
Sep 14 2022 10:12 AM
Jun 02 2023 02:11 PM
Sep 06 2022 09:07 AM
Solution