Forum Discussion
James_Price
Feb 17, 2022Brass Contributor
Project Online Tasks...
Hi team Is it possible for a team member (assuming they have a Plan 3 licence and have a security role of PM or above) to change the start or end day of a task inside their Task sheet? In 'Task Se...
- Feb 17, 2022James --
1. Yes, this is the default behavior of the Tasks page in PWA, and your team members only need a Project Essentials license to do this. This is assuming that the Project Online administrator has not "locked" the Start and Finish columns for editing. The locking of these columns is done in the settings for the My Assignments view, by the way.
2. Yes, this is entirely possible. However, the new settings will only apply to unstarted tasks. Tasks that are in progress will continue to use the old method.
Hope this helps.
James --
1. Yes, this is the default behavior of the Tasks page in PWA, and your team members only need a Project Essentials license to do this. This is assuming that the Project Online administrator has not "locked" the Start and Finish columns for editing. The locking of these columns is done in the settings for the My Assignments view, by the way.
2. Yes, this is entirely possible. However, the new settings will only apply to unstarted tasks. Tasks that are in progress will continue to use the old method.
Hope this helps.
1. Yes, this is the default behavior of the Tasks page in PWA, and your team members only need a Project Essentials license to do this. This is assuming that the Project Online administrator has not "locked" the Start and Finish columns for editing. The locking of these columns is done in the settings for the My Assignments view, by the way.
2. Yes, this is entirely possible. However, the new settings will only apply to unstarted tasks. Tasks that are in progress will continue to use the old method.
Hope this helps.
James_Price
Feb 18, 2022Brass Contributor
Dale_HowardMVP Thanks for this Dale