Forum Discussion
Ylg78
Jun 03, 2024Copper Contributor
Project online error 10102 cannot checkout
Does anyone knows how to fix the error 10102? there is a lot of record of this issue on the web but no solution. Its the one when you try to open a project with the desktop client, pressing the chec...
- Jun 03, 2024I found this thread that is a bit old, nit sure if this is related to my problem.
https://integent.com/microsoft-project-server-2013-root-element-is-missing/
Ylg78
Copper Contributor
I found this thread that is a bit old, nit sure if this is related to my problem.
https://integent.com/microsoft-project-server-2013-root-element-is-missing/
https://integent.com/microsoft-project-server-2013-root-element-is-missing/
Ylg78
Jun 11, 2024Copper Contributor
It looks like I was able to fix it by disconnecting the desktop client from ther PWA through the "manage account" in the "info" menu, then readding the aacount.
all problems are gone.
all problems are gone.