Project Online Custom Field auto-update value
Hello Everyone,
I'm having a custom field called "Sync Status" under Task. Is it possible to auto-update it's value let say to 1 whenever a Task gets modified? Just like a trigger?
Thanks & Regards,
Rohan
1 Reply
- ben_projectBrass ContributorHi, Alas there is no event that flags when a task is modified. https://docs.microsoft.com/en-us/office/vba/api/project.task