Project Online: Create new project - required minimum plan

Occasional Contributor

Hello community,

I have a seemingly answer-easy question I just don't find an answer to on all Project Online help ressources:

Which minimum project plan does one need to create new PWA (online) project - P3 or P5?

Thanks in advance for an answer.

1 Reply
best response confirmed by Dale Howard (MVP)
Solution
Hi Jens, The P3 licence level offers the desktop client, so P3 allows users creating projects in Project Online. They won't have access to advanced features such as Portfolio Management, Resource demand...