Project for the web - Tasks linkage from different projects

New Contributor

Hi, 

Is there any way in MS Project for the web to link tasks (create interdependencies) between different projects?

Thanks!

2 Replies
dmshk --

No, there is no way to create cross-project dependencies between different projects in Project for the Web. Sorry, but hope this helps.
You can use some workaround solutions. 1-st option: to use PowerApps to develop this functionality. In this case you will use task form in the model driven application to select interdependencies and even make some business logic over it. 2-nd option: You can use link to the other project task as a url link in the task attachments pane. This is just for quick view and opening connected task.