Project for the Web: format grid and viewing custom fields/columns in grid in Power BI...
- Aug 15, 2022
Hi James_Price ,
In the Power BI table / grid - can you use the conditional formatting options to colour the table / grid rows as needed? https://docs.microsoft.com/en-us/power-bi/create-reports/desktop-conditional-table-formatting
Custom fields created in Project for the web grid view are not available outside of the Project for the web UI so unfortunately you are not able to include these in Power BI reports.
Paul