Forum Discussion
oskarkuus
Nov 25, 2021Brass Contributor
Project for the web - dataverse change status options of a roadmap/overview?
I work with project for the web and use the overview/roadmap to pull in several projects and get a good timeline for them all. but i want to update the status-options that are available in the ov...
Paul_Mather
Nov 30, 2021MVP
Hello oskarkuus ,
You could update the Row title - see the example where I added "- ACTIVE" to the name:
Maybe this might help to show which projects are active etc.?
Paul
oskarkuus
Dec 01, 2021Brass Contributor
well i guess that is a solution.
but it depends heavly on doing it correctly since my goal is to be able to use tools like powerapps, power automate and power bi... if each project get a status in text in the title... then i cant be sure all project managers have spelled the status correctly etc.
roadmap is one thing. if no status is possible to set there.. fine.
but i cant even demand that my project leaders close a project. it all seems to be controlled by date and that is quite allot of micromanagment fora project manager if a project need be set on hold for a while...
but it depends heavly on doing it correctly since my goal is to be able to use tools like powerapps, power automate and power bi... if each project get a status in text in the title... then i cant be sure all project managers have spelled the status correctly etc.
roadmap is one thing. if no status is possible to set there.. fine.
but i cant even demand that my project leaders close a project. it all seems to be controlled by date and that is quite allot of micromanagment fora project manager if a project need be set on hold for a while...