Jan 31 2022 05:10 AM
Hi There,
I have an interesting problem:
PWA is in SharePoint permission mode.
The user is a member only of the "Team Members for Project Web App" group
When the user log in and click on the Projects he/she is able to see Projects that he/she is not a member of (not an owner nor a participant/resource whatever)
A cannot see any settings to check (If I click on the Project Permission it only redirects me to the Project subsite permission page)
Did I miss something or how Can I make sure people see only those projects that they are assigned to?