Forum Discussion
Chuck_Pollard
Jul 20, 2023Brass Contributor
Project; Bugs, Problems, and Issues - Relationship Issue
Can someone tell me how an activity can be "linked through another chain" with no predecessors or successors?
John-project
Jul 20, 2023Silver Contributor
This might happen if there are dependencies on summary lines. But without seeing more of the file, the exact issue can't be determined.
John
Chuck_Pollard
Jul 20, 2023Brass Contributor
I never tie logic to Summary Tasks; it's just not good practice. Accidents do happen though...
I reviewed the project and no logic was tied to any of the summary tasks. After a Save/Close I was able to make the tie though.
Good looking out none the less. Thanks!
I reviewed the project and no logic was tied to any of the summary tasks. After a Save/Close I was able to make the tie though.
Good looking out none the less. Thanks!