Project; Bugs, Problems, and Issues - Layout / Round Bars to Whole Days
Can anyone help me figure out what would cause this? Bar Configuration before turning OFF round to whole days and after turning off round to whole days I changed nothing othe...
PlannersPlace
Sep 20, 2023Brass Contributor
Maybe use "Baseline Estimated Finish" instead of "Baseline Finish". It worked for me.
After Rounding of Bars to Whole Days
Before Rounding of Bars to Whole Days
=jerome