Project 2010: After filtering just for "necessary" tasks, ... the bars of the GANTT-chart have a gap
Dear all, I am using Microsoft 2010. I have 3 tasks, ... they are aaa, bbb, ccc. I have one user-defined column, called "necessary", where I declare task "bbb" not necessary. Then I filter accordi...
John-project
Jul 22, 2023Silver Contributor
Hans 1958,
I don't know which version changed how the inactivate feature works with respect to re-connecting dependencies. I have Project 2010 and Project 2019, I do not have Project 2013 or Project 2016.
John
I don't know which version changed how the inactivate feature works with respect to re-connecting dependencies. I have Project 2010 and Project 2019, I do not have Project 2013 or Project 2016.
John
Hans1958
Jul 23, 2023Copper Contributor
Hi John,
Thanks so much for your quick answer. It helped me! I'm very grateful for your responses! Wish you well! Keep safe! Hans ... from Germany
Thanks so much for your quick answer. It helped me! I'm very grateful for your responses! Wish you well! Keep safe! Hans ... from Germany