Forum Discussion
jonathanappleyard
Dec 02, 2022Copper Contributor
Printing with Timeline
Hi. Is it possible to print/export to PDF a Gantt Chart with Timeline combined view in MS Project Regards, Jonathan Appleyard
PlannersPlace
Dec 02, 2022Brass Contributor
Not sure it's possible as they are 2 separate views.
Either take a screenshot and print to pdf
or use "Copy Timeline" to paste into a presentation and inserting the pdf of Gantt Chart (assuming it's a single page) into the presentation and then create a pdf of the presentation showing both timeline and Gantt Chart