Nov 11 2021 05:39 AM
Hi,
I'm trying to find the user name who published the project in Power Automate Published trigger. Is there a way to find it?
Nov 11 2021 10:46 AM
Nov 11 2021 11:08 PM
Nov 11 2021 11:33 PM - edited Nov 11 2021 11:34 PM
@Paul Mather Even I was looking for 'checked out by' field in the oData/REST for the specific project but looks like this info isn't exposed. Any API that provides CheckedOutBy/Published By?
Nov 12 2021 12:52 AM
SolutionHello @ramkanumuri ,
When using the Project Online Remote event receivers, that does contain the user details for who triggered that event but this hasn't been exposed in the Power Automate action.
Regarding checked out by, this is available in the REST API but only whilst the Project is actually checked out - there is no history etc. The API method is below:
{pwaUrl}/_api/ProjectServer/Projects('ProjGuid')/CheckedOutBy
Hope that helps
Paul
Nov 12 2021 12:52 AM
SolutionHello @ramkanumuri ,
When using the Project Online Remote event receivers, that does contain the user details for who triggered that event but this hasn't been exposed in the Power Automate action.
Regarding checked out by, this is available in the REST API but only whilst the Project is actually checked out - there is no history etc. The API method is below:
{pwaUrl}/_api/ProjectServer/Projects('ProjGuid')/CheckedOutBy
Hope that helps
Paul