Planned % Complete Vs Duration Variance Vs Actual Complete
Hi, Can there be a scenario in project plan where overall the project duration is delayed, however a task actual % complete can be more that planned percentage calculated based on duration? T...
John-project
Jul 09, 2024Silver Contributor
Greema,
Well I dunno. I'm guessing you are asking because you have such a scenario. If so, could you post a screen shot.
Remember, "planned percentage" will be based on Baseline Duration, not scheduled Duration so I suppose there could be a condition where the actual % complete is greater than the planned % complete. This of course assumes the plan was not re-baselined.
John
Well I dunno. I'm guessing you are asking because you have such a scenario. If so, could you post a screen shot.
Remember, "planned percentage" will be based on Baseline Duration, not scheduled Duration so I suppose there could be a condition where the actual % complete is greater than the planned % complete. This of course assumes the plan was not re-baselined.
John