Where is the pert analysis toolbar in Ms Project 2019 ? I cannot find it. I read in google "to enable the PERT toolbar on the View menu, from the Toolbars menu, choose PERT Analysis" but there is not. What should i do ?
Jun 24 2021 07:59 AM
What you read on Google may have been referring to an earlier version of Project. See the following post:
https://techcommunity.microsoft.com/t5/project/pert-analysis-in-microsoft-project/m-p/906420