Forum Discussion

Kish27's avatar
Kish27
Copper Contributor
Jan 20, 2022
Solved

Overallocation of Resource

Hi I am just doing something very simple but I am just not getting it right. I want to simulate a resource overallocation scenario and would like the red man icon to appear on the indicator column. ...
  • Dale_HowardMVP's avatar
    Jan 20, 2022
    Kish --

    Click the Resource tab to display the Resource ribbon. In the Level section of the Resource ribbon, click the Leveling Options button. In the Resource Leveling dialog, select the Manual option at the top of the dialog, and then click the OK button. Hope this helps.

Resources