Mar 15 2022 08:00 PM
I'm running the MS Project Online Desktop Client and currently working on a reasonably sized project schedule (900 work elements so far). I created a few Timelines for various parts of the Program (Engineering, Production, Delivery, etc) and that all worked OK. I now want to put in an additional Timeline with the key milestones on it and I want it to appear on top of the existing Timelines. However, I cannot for the life of me find any way to rearrange the order of the Timelines.
I can do a workaround by creating another timeline and then renaming all my existing Timelines and moving the milestones/tasks down manually until I have a blank timeline on the top of the screen that I can then populate but I'm hoping that there might be a way to rearrange the Timeline order that I am not aware of?
Thanks in advance for any tips on how to achieve this!!
Mar 16 2022 05:25 AM
Mar 16 2022 02:10 PM
@Dale Howard- thanks!! That's what I thought but I was hoping that there might have been some obscure way of doing it - guess I will just have to do the workaround and manually transfer them all down until I get a blank timeline on the top.
The other feature that would be really handy would be if it was possible to only have the Timescale on the top Timeline - ideally I would like to have a Timescale on it but it just clutters things up when it is on all 4 of the Timelines that I have created.
Mar 16 2022 06:29 PM
Jun 01 2022 07:32 PM
@Gags44 I was looking for the same options here in my huge project with multiple timelines. And I agree on the timescale showing only on top to save space. Looks like I'm not the only one.