Forum Discussion
Gags44
Mar 15, 2022Copper Contributor
MS Project Timelines
I'm running the MS Project Online Desktop Client and currently working on a reasonably sized project schedule (900 work elements so far). I created a few Timelines for various parts of the Program (E...
Mar 16, 2022
Gags44 --
Interesting question. Like you, I am not able to rearrange the timelines in the Timeline view. It appears that Microsoft Project arranges them in the order they were created, with no option to move them around. I do not see any workaround to this limitation. Sorry, but hope this helps.
Interesting question. Like you, I am not able to rearrange the timelines in the Timeline view. It appears that Microsoft Project arranges them in the order they were created, with no option to move them around. I do not see any workaround to this limitation. Sorry, but hope this helps.
Gags44
Mar 16, 2022Copper Contributor
Dale_HowardMVP- thanks!! That's what I thought but I was hoping that there might have been some obscure way of doing it - guess I will just have to do the workaround and manually transfer them all down until I get a blank timeline on the top.
The other feature that would be really handy would be if it was possible to only have the Timescale on the top Timeline - ideally I would like to have a Timescale on it but it just clutters things up when it is on all 4 of the Timelines that I have created.