James_Price
Jun 14, 2021Brass Contributor
MS Project timeline labels are wrong...
Hi team In MS Project Gantt, when I tick on the 'Use fiscal year' box, the labels change to the previous year. And this is exactly what's happening in the Timeline view. The starting task is 8 Jan...
- Jun 15, 2021James -- Did you set the starting month of the fiscal year on the Schedule page of the Project Options dialog? If so, did you select the checkbox named Use Starting Year for FY Numbering? Please let us know and we will try to help you.
John-project
Jun 20, 2021Silver Contributor
Dale already answered your question but he may not be on-line today so please allow me to make an observation. The months and years stated in your last posting do not match the screen shot posted. The screen shot shows Jan '21 through Apr '21 and then May 22' to Apr '22 for the Timeline view. The Gantt Chart timescale shows Jan '21 through Apr '22 as a "normal" year. That presentation is synonymous with Project > File > Options > Schedule tab set for a "fiscal year starts in" May and the Gantt Chart timescale option for "use fiscal year" unchecked.
No strange display behavior, just an inconsistency with fiscal year settings.
John
James_Price
Jun 20, 2021Brass Contributor
Hi John
Many thanks for this. I thought if I unticked the 'use starting year in FY numbering' that would be enough but clearly not 🙂
Cheers
James
Many thanks for this. I thought if I unticked the 'use starting year in FY numbering' that would be enough but clearly not 🙂
Cheers
James
- John-projectJun 21, 2021Silver ContributorJames,
You're welcome and thanks for the feedback. Glad you got it cleared up.
John