MS Project Online - Providing Viewer Access for those without a License
Dale_HowardMVP - Thank you for the information. I have the setting correct now.
Team members have been set up as "User can be assigned as a resource."
I believe I am clear on your comment, "All of your PWA users will need licenses, including your stakeholders."
What I want is to set up people as Guests. Our rationale for purchasing Project Online in part was because it is advertised as allowing non-licensed "Guests" viewing access to project plans.
https://support.microsoft.com/en-us/office/let-guests-see-your-project-in-project-for-the-web-81e1c210-74b2-4711-98ab-dea58f1b566b
I've tried to follow the steps in the article to no avail. It seems that I have set up someone as a Guest in Microsoft 365, not Project Online.
The article refers to setting up guests in the Project for the Web application. What you have set up is your Project Online application whose web-based user interface is known as Project Web App. Yes, I know the names are confusing. You can blame this on Microsoft Marketing.
So, are you planning on using Project Online or Project for the Web? Please confirm which one you want to use as I am confused about your plans.
- Berto2033May 05, 2023Copper Contributor
Project Online. I'm basing that on this view...
- May 05, 2023Berto2033 --
You cannot provide guest access to Project Online without providing an Office 365 license (Project Plan 3 or 5) and without creating a user account for your guest. You CAN provide guest access in Project for the Web, but that tool was WAY LESS features and functionality than you will find in Project Online. Sorry, but hope this helps.