Forum Discussion
ArcherJayden
Mar 13, 2023Copper Contributor
MS Project Online - Project Level Custom Field Number Format
Hi,
I have created a custom field with number data type which is an identifier to Project Id that will be used later to link external projects coming from different PMO tool.
I can’t find a way to format this custom field to eliminate commas in Project Server online.
I have called this number field into another field with formula = Format([custom field], “##”)
The above returns blank when I add to Project Summary view on MS Project center.
Anyone has any recommendations or suggestions?
1 Reply
Hello ArcherJayden ,
The number format with commas etc. is not configurable. I think from memory the format will come from the regional settings of the site collection.
Regarding your formula field being empty, you'll need to open the project/s, recalculate and publish each project for the formula field to calculate and have a value.
Paul