MS Project not re-calulating units when changing task duration
Given I have a task set to Type="Fixed Work" and Task Mode = "Auto Schedule" and I have set Work and Duration to fixed numbers, when I increase duration and select "Decrease the hours resources work ...
Ignacio_Martin
Jan 25, 2023Steel Contributor
Hello It is certainly confusing the value that is displayed in the task view. In the Task Usage or Resource Usage view, automatic changes to the resource's Assignment Units are displayed