Forum Discussion
BlakeBennett2020
Feb 02, 2023Copper Contributor
MS Project ##### Issue
Very frustrating issue with MS project, all of a sudden my milestone tasks have ##### and the overall look of my MS project has changed. This does not happen to others when they open my programe, t...
John-project
Feb 03, 2023Silver Contributor
BlakeBennett2020,
What happens if you expand the Duration field column? In the back of my mind I seem to recall another user who had an issue similar to yours (i.e. string of #####) but I'm not sure I can even find that post.
I notice all the task lines with the issue are in red font indicating you customized either the Text Style for milestones or the Task font for those lines. Does the issue go away if you change those lines to the default Calibri 11 font?
John
What happens if you expand the Duration field column? In the back of my mind I seem to recall another user who had an issue similar to yours (i.e. string of #####) but I'm not sure I can even find that post.
I notice all the task lines with the issue are in red font indicating you customized either the Text Style for milestones or the Task font for those lines. Does the issue go away if you change those lines to the default Calibri 11 font?
John