Dec 08 2017 12:59 AM
Hi All,
I am new to Project Management as I have started a new role as a Project Lead and this is all new to me coming from a tester background.
I have been tasked with finding a way on MS Project to show tasks that are due in 30 60 and 90 days, however I have no ideas. I was wondering if anyone has a way of doing this on a existing project.
any other advice is welcome...
Thank you All!!
Yash Dutt
Jun 05 2018 11:34 PM
Yas
You can do a 30, 60 day look up
I use this flag and view for a 4 week look ahead
Create a Flag custom field with the following formula (you can change the 4 weeks)
IIf(([Start]>=DateAdd("ww",-1,[Status Date]) And [Start]<=DateAdd("ww",4,[Status Date])) Or ([Finish]>=DateAdd("ww",-1,[Status Date]) And [Finish]<=DateAdd("ww",4,[Status Date])),Yes,No)