MS Project 2019 and Planner

Brass Contributor

Hi,

 

Can one connect MS Project 2019 with MS Planner? What are the steps.

 

Thanks,

Teshome

3 Replies
Teshome --

You can only connect an MS Planner project in Microsoft Project is your project is an enterprise project stored in Project Online. There is no way to connect a desktop only project (saved as an MPP file) to a Planner project. Hope this helps.
Dale,

Thank you for getting back to me. Planner has an export Excel option. However, it doesn't filter specific tasks under the planner; any suggestions?

Regards,
Teshome
Molalenge --

If you apply the Board view in Planner, you can click the Filter button in the upper right corner of the page. There are a number of built-in filtering options on the menu. If none of those work for you, however, you would need to filter the data in Excel. Just a thought. Hope this helps.