Microsoft Projects timeline not working correctly?
Hey there, I have been looking high and low for an answer on this, but cannot seem to find an answer anywhere. I have set non-working times in my calendar. They are showing in the timeline but ac...
Jan 05, 2021
WayneStrydom --
Go to the Resource Sheet view in your project. For each Work resource in your project, set the Base Calendar value to the calendar in which you entered nonworking time. Please let us know if this helps.