Aug 29 2022 10:04 AM
Hello,
I have a task with 2 resources. 1 resource has baseline work of 10hrs and remaining work of 0hrs. The 2nd resource has baseline work of 0hrs and remaining work of 10hrs. When I "Mark on Track", the resource with remaining work goes to 100% complete and the remaining work switches to actual work of 10hrs. The resource with baseline work remains at 0% complete though resulting in the task being at 99% complete. Why does the Mark on Track option not mark both resources at 100%?
Thank you!
Aug 29 2022 04:21 PM
Aug 31 2022 07:38 AM
Good Morning,
Sorry about that. Please see screenshots below.
*We set the baseline with one resource and then reassign the work/remaining work to another resource.
Before Mark On Track:
After Mark on Track:
Aug 31 2022 09:53 AM
SolutionAug 31 2022 11:27 AM
Aug 31 2022 12:57 PM