Jun 14 2023 10:58 PM
Hi,
I am using Project professional. When I start the Project in my computer, there are so many Profiles which are created automatically. I have no idea why there are so many profiles..
How do I remove others and keep only one profile?
Jun 15 2023 06:01 AM
Jun 15 2023 01:32 PM
Solution@Joey_Cho - I've seen this with several of our users. This tends to happen if you open a project from the PWA in Project desktop and while it's open you lose your network connection, you forget to check the project in, etc. I'm sure there are other things that may cause this, but the fix is simple (usually).
Remove unwanted Login Profiles
1. Open MS Project
2. Click 'Options' at the bottom right hand corner
3. Click 'Cancel' on 'Project Options' dialog
4. On the menu bar select 'File, Info'
5. Click the 'Project Web App Accounts' button on the 'Info' page
6. Select the invalid/corrupted entries then click 'Remove'. Repeat as needed
I'd also suggest you delete your local MSP cache.
Delete Cache
Jun 20 2023 12:51 AM
@RodFromm Thank you so much. I removed all messy profiles! Thanks!
Jun 20 2023 05:06 AM
@Joey_Cho Glad to help. Thanks for replying and letting us know it resolved your issue.
Jun 15 2023 01:32 PM
Solution@Joey_Cho - I've seen this with several of our users. This tends to happen if you open a project from the PWA in Project desktop and while it's open you lose your network connection, you forget to check the project in, etc. I'm sure there are other things that may cause this, but the fix is simple (usually).
Remove unwanted Login Profiles
1. Open MS Project
2. Click 'Options' at the bottom right hand corner
3. Click 'Cancel' on 'Project Options' dialog
4. On the menu bar select 'File, Info'
5. Click the 'Project Web App Accounts' button on the 'Info' page
6. Select the invalid/corrupted entries then click 'Remove'. Repeat as needed
I'd also suggest you delete your local MSP cache.
Delete Cache