Last Saved Project Baseline date stored on SQL database
I am using Professional 2019 and on Prem Project server 2019. Project is baselined on Professional or in PWA (Project web app), through Set baseline option. I am looking for the date that the baseli...
Paul_Mather
Apr 15, 2024MVP
Hello Ana-S ,
No it won't work for baselines created in the PWA UI. The out of the box date is not available to query in a supported way in the DB as it is not in the reporting schema.
Paul
Ana-S
Apr 15, 2024Brass Contributor
Oh I see. Wish they published that information so we could pick that information on our SSRS. Even if it stored in published or draft schema, it would be easy to pick without putting workaround.
Thank you Paul.