Forum Discussion
Lola_Amusa
Apr 25, 2022Copper Contributor
Inserting a Summary Task and the subsisting tasks
Hi there, I want to perform a task similar to inserting a subprojects to create a consolidated Plan. However, I do not want to insert the whole project in the consolidated plan. I only want to inse...
- Apr 25, 2022Lola_Amusa,
You have two options. One, copy and paste the selected summary with its subtasks into your consolidated plan. Two, insert as a subproject but uncheck the "Link to Project" option below the file selection list in the Insert Project window. Then delete those parts of the inserted plan that you don't want in your consolidated plan.
Neither of these methods will create a dynamic link, a dynamically linked structure can ONLY be achieved with insertion of a full file.
John
Lola_Amusa
Apr 27, 2022Copper Contributor
Thanks John-project . I was actually thinking dynamic link such that once the section is updated in the subsisting project the update automatically filter through the Consolidated plan when I open it. Thanks anyway- I wasn’t sure if I was pushing my luck to much 😁
John-project
Apr 27, 2022Silver Contributor
Thanks for the feedback. If I answered your question, please consider marking my response as the answer.
John