Forum Discussion

Lola_Amusa's avatar
Lola_Amusa
Copper Contributor
Apr 25, 2022
Solved

Inserting a Summary Task and the subsisting tasks

Hi there, I want to perform a task similar to inserting a subprojects to create a consolidated Plan. However, I do not want to insert the whole project in the consolidated plan.  I only want to inse...
  • John-project's avatar
    Apr 25, 2022
    Lola_Amusa,
    You have two options. One, copy and paste the selected summary with its subtasks into your consolidated plan. Two, insert as a subproject but uncheck the "Link to Project" option below the file selection list in the Insert Project window. Then delete those parts of the inserted plan that you don't want in your consolidated plan.

    Neither of these methods will create a dynamic link, a dynamically linked structure can ONLY be achieved with insertion of a full file.

    John

Resources