Forum Discussion

robertpoddar's avatar
robertpoddar
Copper Contributor
Jul 14, 2022

Importing a plan from Google Sheet

Hi,  Earlier I was using Smartsheet project management tool and now corporate has moved us into MS Project Online. I had exported a Smartsheet plan into Google Sheet.    How do I import the Google...
  • Dale_HowardMVP's avatar
    Dale_HowardMVP
    Jul 21, 2022
    Robert --

    I ran into this exact problem when I exported a project from Project for the Web to an Excel workbook. When I tried to import the workbook into Microsoft Project, the From: Excel field rows were blank in the Import Wizard dialog.

    Oddly enough, I was able to resolve the problem by copying and pasting the contents of the original Excel workbook into a totally new blank workbook and then saving it with a different name. I would suggest that you try this method to see if it resolves your problem as well. Hope this helps.

Resources