Oct 16 2022 07:47 PM
Hi there,
On the following link, it says the following "By default, changes to a task's percent complete value affect the actual work value. Similarly, changes to the actual work value affect the task's percent complete value. You can change this default and have percent complete and actual work independent of one another in the Project Options dialog box."
I have done the following:
In File > Options > Schedule > Calculation options for this project >[UNTICK]: Updating Task status updates resource status
However, when I created a test project, assigned myself a task where
Work = 6 hours; Duration = 1 day
Published to PWA
Using Tasks dashboard, change Actual Work = 2 hours, and used Mark Complete to mark the task as complete. However, this changed the Actual Work to be back to the initially scheduled Work value of 6 hours.
I want to be able to mark Actual Work as 2 hours, as we are using templates with approximate values for Work and then use the values tracked for Actual Work to refine the template values,
Are there other options to change so that this can happen?
Oct 17 2022 07:22 AM
SolutionOct 17 2022 01:21 PM
Awesome, thank you so much again Dale, that does make sense.
Another related question, is there any way to auto fill in the Actual Finish date as the date the Task was marked completed?
Oct 17 2022 07:22 AM
Solution