How to Drive 1 Resource to Do 2 Simultaneous Tasks - Same Days, 50% Allocation to Each
John,
My (more complicated) setup looks similar to what you have above. Both activities have the same predecessor and are allocated at 50%, and the project has been updated and leveled. The sequence that is supposed to be concurrent (see screen shot) repeats a few times as we do the cycle of tasks repeatedly at multiple locations, but it seems only one instance of this has stacked up as concurrent - the rest are all going sequentially (sometimes task 1 goes first, sometimes task 2 first, not sure why either).
Let me know if the attached screenshots help at all.
EDIT: wouldnt let me attach the screenshot in the body for some reason so it's here as an attachment
You say you used leveling and that is the most likely reason for the non-concurrency. Why the tasks are concurrent in one case but not in others, I can't tell without actually looking at your file.
When you leveled, did you level the whole project or do selective leveling?
John