Feb 12 2022 05:04 AM
Feb 14 2022 05:56 AM
Feb 14 2022 06:40 AM
Feb 15 2022 05:19 AM
Feb 15 2022 05:29 AM
Feb 15 2022 06:55 AM
Feb 15 2022 07:26 AM
Feb 15 2022 07:48 AM
Hi all,
thank you for the many replies. I am using MS Project Professional 2016.
I'll try to explain again the details (and as I said before, I am new to the software).
I have a task which can be started from a certain date and must be finished by a certain date. But the amount of hours paid by the project is fixed. The contractors assigned to the task can start to work on it and book hours to the task whenever they want (after the start date) but they don't necessary need to start on the defined start date. Of the three resources assigned 1 would get 60% of the available amount of hours, the second one 20% and the third one 10%.
Thank you for your help.
Luca
Feb 15 2022 02:14 PM
SolutionFeb 16 2022 09:34 AM
Feb 15 2022 02:14 PM
Solution