01-07-2020 05:10 PM - edited 01-07-2020 05:12 PM
I have got a schedule template with a list of the tasks with links, duration and calendar etc. Now, I have to create the individual project schedule using this template, but not all the tasks are required for every project. Is there a way where I can provide the opportunity to the user where they can answer few questions (for example yes or no) and that will generate a schedule with tasks relevant to their project?
01-09-2020 06:33 AM
Click New and complete the fields in the Filter definition box. For the first condition ignore the And/Or column. Under Field Name select the field that you want to filter on, then select the test for example, contains or equals. Finally select the value.
I hope this information helps!
Regards,
Lewis