Does anyone know how project determines whether a task's status is Late or On Schedule? I have a task for example that is showing as "On Schedule", even though it's actual start was 7/20 opposed to its baseline start of 7/18, it is 75% complete, however its baseline finish was supposed to be 8/2. The current Planned start and finish dates are 7/18-8/15.
So it would appear that project considers a task to be On Schedule not factoring in baseline dates? But current planned versus actual dates and % Complete?
Aug 09 2022 12:41 PM
I suggest you hover your mouse over the title on the Status field and then hit F1. That will bring up Project's help file. Type "Status" into the search bar and then select, Status (task field).
If you have further questions after reading the help file, let us know.
John