How do I import my plan in excel to project for the web

Copper Contributor

Please I have my project planned in excel. How can I import it into Microsoft project for the web? What I see is to import mpp file but not excel. Is there a way to go around it?

2 Replies
@Paul Mather is this something you can help with - importing my project plan from excel into Project for the web
Richiee --

There is currently no way to import a project from Excel into Project for the Web. You could probably copy and paste the task names, but that's about the best you can do. Sorry, but hope this helps.