How can I edit 'inactive' tasks in PWA?

Occasional Visitor

Due to the nature of our projects, we have activities in our schedules that we want to make 'inactive'.  In MS Proj Professional, we have put a 'No' in the Active field to inactivate them.

 

The PMs that manage these schedules are doing so through PWA.  When they open those same projects in PWA, the tasks with Active = 'No' are not editable.  They are not even able to change the Active field from 'No' to 'Yes'.

 

Is this by design?  How can I enable them so that they have the ability to make their tasks Active as needed?

 

Thanks in advance.

1 Reply

Hello @heyfred3 ,

This field is a Project Professional / Project Online Desktop field and not editable in PWA.

https://support.microsoft.com/en-us/topic/b588a7f4-3008-45ab-947b-2140b0b694bd 

Paul