Forum Discussion
ashpandit9
Sep 22, 2021Copper Contributor
Hours assigned to Resources
I have assigned a resource (with 3% units) to a task which has a duration of 3 months. When I generate a work report and see resource usage across two months, looks like the resource is working more ...
ashpandit9
Sep 27, 2021Copper Contributor
Thanks John. I'm not sure if your address had two 'dots'. Anyway, I figured the issue. My hours were changing because of chopping and changing of my durations and resource allocations. If I delete the resource allocation cells and then paste again, it gets realigned as desired. Thanks for your help!
John-project
Sep 27, 2021Silver Contributor