Forum Discussion
Historic RAG
Thanks Paul_Mather - really helpful. One question is there a way to gather from multiple lists into one list? The lists all sit on the individual project sites. I am trying to find a way round the fact that the PowerBI content pack for PWA only draws from native fields, not custom one.
Thanks again!
Paul
Hi pauleast ,
You could build a process to push the data from all Risks lists etc. into one central list on the PWA site etc. or better still push it to something like Azure SQL DB then report of the SQL Database. There are many example 3rd party tools out there from Project partners that do this. We typically push all of the PWA data into an Azure SQL database (project, tasks, assignment, project site list data etc.) into an Azure SQL database and report from that.
Paul
- pauleastDec 20, 2019Copper Contributor
Hi Paul_Mather
Might be a little outside of my skill set! Guessing that means there isn't a way with Flow to do this:(
Appreciate your help!:)
- Paul_MatherDec 20, 2019MVP