Hide Grouping titles and header names
- Feb 14, 2024
Hello, Robert.
Unfortunately your grouping fields are not Lookup (List) type, but if you have a exceptional need and want to try:
- Create 2 custom text fields Lookup type(Custom attributes in the form)
- Select the option "Allow additional items to be entered into the fields"(into Lookup Table)
- Close
- Copy and paste Project and Resource Initials columns into the new custom fields respectively
- Group finally by these two Lookup fieldsIt is a momentary solution for an emergency.
Ignacio
Hello, Robert.
Unfortunately your grouping fields are not Lookup (List) type, but if you have a exceptional need and want to try:
- Create 2 custom text fields Lookup type(Custom attributes in the form)
- Select the option "Allow additional items to be entered into the fields"(into Lookup Table)
- Close
- Copy and paste Project and Resource Initials columns into the new custom fields respectively
- Group finally by these two Lookup fields
It is a momentary solution for an emergency.
Ignacio