May 02 2023 10:28 PM
Hi Guys,
Can you please assist me on the following. I cannot find the problem. On my MS Projects Schedule I have the following:
% Planned and % Complete
Now here is the thing. I can only get a value % after I put in a number of days, but I do not want to do that as it is a milestone. The day must stay 0. If I make the number of days 0 then I do not get a % value, How do I change that again, please?
May 03 2023 01:02 AM
As per attachment. You will see the parts that is marked yellow. On the % Planned it give me a value but on % Complete it do not give me a value. As per my previous question, if you add days to the milestones then the % complete is correct but as I mentioned it is a milestone and I cannot add days.
May 03 2023 08:42 AM
May 09 2023 11:35 PM
@John-project
Thank You so much for your explanation. Do you perhaps know of a formula I can use just for testing purposes?
May 10 2023 09:12 AM
SolutionHere is a sample plan with a group of milestones under a summary line. The Number1 field is customized with the formula shown. The summary line is set to sum up the number of completed milestones.
Hope this helps.
John
May 18 2023 07:38 AM
@John-project Thank You so much. I have tried the formula on myside but it still give me a syntax error. I also tried to retype it again but it still give me a syntax error.
Can you please assist?
May 18 2023 08:10 AM
I would help if you would post your formula. However, it may be as simple as changing the delimiter, which is a comma on my system, with a semicolon, which may be the delimiter on your system. For example, try this syntax:
IIf([Milestone]=True And [% complete]=100;1;0)
John