Forum Discussion

ahobbi695's avatar
ahobbi695
Copper Contributor
Sep 20, 2024
Solved

Having trouble showing number of days.

Hello all,   New to Project and when I input 60 days I want it the duration to be 60 days. Below I have a screenshot showing that when I put 60 days in duration in 1.5 it gives a finish date of 12/...
  • John-project's avatar
    Sep 21, 2024
    ahobbi695,
    That's probably because you are thinking in calendar days and that's not how Project works. Project schedules in working days and working days are determined by the Project Calendar. The Standard Project calendar, which is the default, is 8-5 Monday through Friday. So, if a task starts on 9/20/24 and the duration is set at 5 days, that task will show a finish date of 9/26/24.

    If you really want calendar days, you can create a custom calendar (e.g. 6 day workweek, 7 day workweek, etc.) or you can enter duration values in elapsed days (i.e. 5 ed).

    John

Resources