ahobbi695
Sep 20, 2024Copper Contributor
Having trouble showing number of days.
Hello all,
New to Project and when I input 60 days I want it the duration to be 60 days. Below I have a screenshot showing that when I put 60 days in duration in 1.5 it gives a finish date of 12/18/2024.
Any help would be greatly appreciated!
Example:
Today is 9/20/2024, duration of 5 days should = 9/25/2024.
- ahobbi695,
That's probably because you are thinking in calendar days and that's not how Project works. Project schedules in working days and working days are determined by the Project Calendar. The Standard Project calendar, which is the default, is 8-5 Monday through Friday. So, if a task starts on 9/20/24 and the duration is set at 5 days, that task will show a finish date of 9/26/24.
If you really want calendar days, you can create a custom calendar (e.g. 6 day workweek, 7 day workweek, etc.) or you can enter duration values in elapsed days (i.e. 5 ed).
John