Giving the Gantt Diagram in MS Project a title ?

Hi, is it possible to give a Gantt Diagram in MS Project a title which is visible above the bars ?   Regards, mainze
  • Dale_HowardMVP's avatar
    Sep 27, 2023
    mainze5 --

    In his excellent reply, John has given you a good potential solution. The other solution, which I don't think you will like, is to click the Drawing pick list button in the Drawings section of the Gantt Chart Format ribbon, and to select the Text Box item. You can fill in the name of the project in the text box and place it wherever you want it in the Gantt Chart view. However, where things get messed up is when you zoom in our zoom out in the Gantt Chart view, which is why I think you probably won't like this option. But just an additional choice for you to solve this problem. Hope this helps.