HELLO I WANT TO ASK YOU IF I CAN INSERT START TO START BETWEEN TASKS IN GANTT CHART.

5 Replies
ttt_tt --

Yes, this can be done pretty easily. First apply the Gantt Chart view and then drag the split bar to the right edge of the Predecessors column. Select the two tasks that need to start at the same time and then link them with the default Finish to Start dependency. In the Predecessors column for the SECOND of these two tasks, you should see the ID number of the other task. Add the letters SS to the ID number (for example, 9SS) and then press the Enter key. Hope this helps.

THANK YOU. DOES THIS ALSO APPLY TO MS PROJECT FOR THE WEB?
tttt_tt --

No, it does not. Project for the Web currently offers only the Finish to Start dependency relationship between tasks. Sorry, but hope this helps.
Hey, in case you need more information about the Gantt chart and a good example, visit https://www.toolshero.com/project-management/gantt-chart/. Worth a visit! 😉
benblogs800,
Although your link points to a website that does provide instructional information it also promotes products for sale. Such promotion is not allowed by the rules of this forum.